Judgments

Decision Information

Decision Content

A-57-73
Jasmin Construction Inc. (Appellant) (Respond- ent in Cross-Appeal)
v.
Resolute Shipping Limited (Respondent) (Appel- lant in Cross-Appeal)
Court of Appeal, Jackett C.J., Pratte J. and Hyde D.J.—Montreal, September 26; Ottawa, December 13, 1974.
Maritime law—Contract for carriage of goods by water— Fixed price—Excess of weight about 30% more than stipu lated in contract—Whether breach of contract—Amendment of statement of claim to include claim for damages because of inaccurate information—Counterclaim and cross-appeal for alleged damages to cargo—Federal Court Rule 1104.
Appeal from a judgment of the Trial Division maintaining an action on a breach of contract for the carriage by the respondent of 14 mobile medical units from the Port of Quebec to the Ports of Broughton Island North West Terri tories and Clyde River, Baffin Island North West Territories aboard the vessel Tavastland. The action was based on costs incurred by the respondent as a result of an increase in weight of the cargo by about 30% more than the weight estimated by the said respondent which was the basis for making the fixed price offer for the transportation opera tion. The respondent also claimed for a toll charge for top wharfage of $110.61 owing to the National Harbours Board and $1,000 expended on insurance because of the failure of the appellant to supply a letter of credit.
The appellant counterclaimed for $2,707.61 being the amount suffered in damages by the fall overboard of one of the units at the time of loading.
The Trial Judge assessed the additional expenses incurred by the respondent at $24,722.88 as a result of the excessive weight of the cargo and allowed the claim on the basis of unjust enrichment. He also allowed the claim for top wharf- age and the insurance. On the appellant's counterclaim the Trial Judge allowed only one-fourth to the appellant because of negligence of the crane operator and three-fourths to the respondent because of appellant's negligence in giving inac curate information as to weight of the cargo.
Held, allowing the appeal, the Trial Judge erred in basing the claim on unjust enrichment when the action was found ed on breach of contract. In delivering the cargo on the dock near the respondent's ship, the appellant performed one of its obligations under the contract and the fact that both parties were mistaken as to the weight did not constitute a breach of contract on the part of the appellant. Although an amendment to the statement of claim was allowed under
Rule 1104 of. the Federal Court Rules which permitted a claim for damages in tort against the appellant for the giving of inaccurate information on the weight of the cargo, the action must fail since the evidence shows that both parties were aware that the weights were only approximate weights; there was no undertaking on the part of the appellant to pay any additional charges and the respondent carried the cargo at its own risk in determining to enter into that contract. The Trial Judge's decision as to top wharfage charge and insur ance charge should not be disturbed.
As to the counterclaim, the fall of the unit at the time of loading was caused exclusively by the respondent's negli gence in not ascertaining the weight of the units before loading them or using a crane powerful enough to lift weights heavier than those mentioned.
APPEAL. COUNSEL:
Denis Rousseau for appellant (respondent in cross-appeal).
W. David Angus for respondent (appellant in cross-appeal).
SOLICITORS:
Rousseau & Charbonneau, Quebec, for appellant (respondent in cross-appeal). Stikeman, Elliott, Tamaki, Mercier & Robb, Montreal, for respondent (appellant in cross-appeal).
The following are the reasons for judgment delivered in English by
JACKETT C. J. AND PRATTE J.: This is an appeal from a judgment of the Trial Division [not reported, T-3922-71] in favour of the respondent for $25,833.49 with interest and costs, and both an appeal and cross-appeal against a judgment of the Trial Division allow ing the appellant $676.90 with interest and costs on a counterclaim, "which amount" the judg ment provided "can be set off against the amount awarded plaintiff in the principal action".
The principal action was for breach of con tract and the statement of claim reads, in part, as follows:
1. During the month of August 1971, Defendant approached Federal Commerce and Navigation Company Limited (here- inafter referred to as Federal), as duly authorized agent of
Plaintiff, for the carriage by Plaintiff of fourteen mobile medical units from the Port of Quebec, Province of Quebec, to the Ports of Broughton Island, North West Territories, and Clyde River, Baffin Island, North West Territories, on board the vessel TAVASTLAND, operated by Plaintiff;
2. Negotiations were entered into and an agreement con cluded, the agreement between Plaintiff and Defendant being reflected in telexes dated August 27, 1971 and Sep- tember 2, 1971, and in a letter dated September 7, 1971, all three documents being produced herewith as Exhibit P-1 as if herein recited at length;
3. Plaintiff has fulfilled each and every one of the obliga tions undertaken by it in the said agreement, and in particu lar and without restricting the generality of the foregoing Plaintiff duly carried Defendant's cargo to and delivered it in good order and condition at the said Ports of Broughton Island and Clyde River, North West Territories;
4. Defendant, on the other hand, has substantially breached the said agreement, said breaches having caused Plaintiff considerable prejudice and damages;
5. Without limitation of the generality of the foregoing, Defendant has breached the said agreement in that:
(a) The mobile units presented for shipment by Defendant weighed considerably more than the weights as stipulated and represented by Defendant to Plaintiff during the period when the contract of carriage was negotiated and agreed;
(b) Defendant failed to present the cargo for shipment and loading during normal working hours on the agreed date;
(c) Defendant failed to furnish a letter of credit in accord ance with the said agreement;
(d) Defendant failed to insure the cargo in accordance with the said agreement;
(e) Defendant has refused to remit to Plaintiff the amount claimed for top wharfage, the whole in accordance with the custom of the trade and with the said agreement;
6. As a result of Defendant's breach of contract, Plaintiff has suffered a loss of at least $36,787.18 detailed as follows:
(a) Extra costs in receiving cargo after hours $ 898.11
(b) Top wharfage 185.58
(c) Insurance 1,000.00
(d) 3 days extended loading time due to over
weight of the units 8,550.00
(e) Extra expenses for crane equipment and labour as a result of the overweight of the
medical units 11, 603.49
(f) Special survey resulting from the over
weight of the said units 300.00
(g) Lost time during the voyage and lost time at Broughton Island due to the overweight of
the said units 14,250.00
TOTAL $36,787.18
7. At all times material hereto, Federal was acting solely as agent of Plaintiff, Plaintiff being the principal, the carrier and the operator of the vessel TAVASTLAND;
On the appeal, the respondent was given leave to amend by adding the following paragraph:
10. Furthermore, and under reserve of the foregoing, Plain tiff states that Defendant is legally liable in delict (tort) to pay to it the aforesaid sum of $36,787.18 in that Defendant, as a result of its negligence, want of skill, imprudence and fault, provided it with inaccurate information as to the weight of the aforesaid 14 units and failed to provide a letter of credit.
The counterclaim is for $2,146.89 for failure to deliver in good order the goods that were the subject matter of the contract referred to in the statement of claim.
The facts are not really in dispute in their essential details.
In early August, the appellant and the respondent were negotiating a contract along the general lines represented by a telex dated August 6, 1971, from the respondent's parent company to the appellant reading as follows:
[TRANSLATION] IT IS AGREED BETWEEN MESSRS JASMIN CON STRUCTION INC., SHIPPERS, AND FEDERAL COMMERCE AND NAVIGATION CO. LTD., AGENT FOR MESSRS RESOLUTE SHIP PING LTD., SHIPOWNERS, THAT THE AFOREMENTIONED PAR TIES UNDERTAKE THE FOLLOWING:
1. THE SHIPPER TO MAKE AVAILABLE, AND THE SHIPOWNER TO CARRY, THE FOLLOWING CARGO:
14 HOUSE TRAILERS OF THE SIZES DESCRIBED BELOW:
12 UNITS 52 FEET LONG
12 FEET WIDE 14 FEET HIGH
2 UNITS 52 FEET LONG
8 FEET WIDE 14 FEET HIGH
(HEIGHTS EXCLUDING WHEELS, WHICH MAY BE REMOVED WITHOUT DIFFICULTY AT THE OPTION OF THE SHIPOWNER) TWO UNITS WEIGH 30,000 LBS AND THE TWELVE OTHERS ABOUT 20,000 LBS EACH.
WITH THE UNITS ARE INCLUDED ABOUT THIRTY TONS OF BUILDING MATERIALS WHICH THE SHIPOWNER MAY USE FOR TRIMMING, BUT THE LENGTHS OF WOOD SHALL UNDER NO CIRCUMSTANCES BE CUT.
2. THE SHIPOWNER SHALL TRANSPORT ALL UNITS ON THE DECK OF THE M.V. "TRULELAND", BRITISH REGISTRY AND CLASSIFIED "LLOYDS ICE CLASS 1"
3. APPROXIMATE DATES OF LOADING: SEPTEMBER 15, 1971.
4. FREIGHT PAYABLE BY THE SHIPPER TO THE SHIPOWNER C.C. $14,000 (FOURTEEN THOUSAND DOLLARS) PER UNIT ON A MINIMUM FOURTEEN UNITS.
5. THE SHIPPER SHALL DELIVER THE UNITS TO THE WHARF AT QUEBEC CITY; THE SHIPOWNER SHALL LOAD AND DELIVER SEVEN UNITS TO THE SITE AT BROUGHTON ISLAND AND SEVEN UNITS TO THE SITE AT CLYDE RIVER, BAFFIN ISLAND, AT WHICH LOCATIONS THE SHIPPER WILL USE A BULLDOZER WITH THE NECESSARY ATTACHMENTS TO REMOVE THE UNITS FROM THE BARGES.
6. NO INSURANCE ON THE VESSEL, EVEN IF INCURRED ON A VOYAGE TO THE AFOREMENTIONED LOCATIONS, SHALL BE PAYABLE BY THE SHIPPER.
7. THE SHIPPER SHALL BE RESPONSIBLE FOR ALL INSURANCE PREMIUMS REQUIRED ON THE CARGO FROM THE WHARF AT QUEBEC CITY TO THE SITES AT BROUGHTON ISLAND AND CLYDE RIVER.
The information contained in this telex about the weights of the objects to be carried was obviously a matter of special concern to the respondent, which company was negotiating a contract to carry some very large objects as deck cargo on one of its vessels. Helge Tomter, Commercial Manager for the respondent, had been away from Montreal during the first half of August and he testified, concerning the time after his return, as follows:
Q. Could you tell the Court as much as you can about weights, your efforts to find out about the weights and what you were told and who you were dealing with at the Defendant Company?
A. Yes. We felt that it was important that we should get more information about the weights; the term "approx- imately" we don't like it very well, and we found it was an important factor to have established as much as possible. In the end of August, one of the super- cargoes, Captain Kuyper, and myself—well, I should say that in the interim we had been in touch with Jasmin Construction, Mr. Proulx, and we asked repeat edly for the exact weight for each unit, and the impres sion we had been left with was that these weights were not, would not be available to us—
Mr. Tomter was sufficiently concerned about the weights at that time that he ascertained from the appellant the name of the company that was supplying the objects in question, which was a company called "Treco" in Quebec City, and he obtained permission from the appellant to go to
Treco's premises to "inspect" the units. He and a Captain Kuyper thereupon went to Quebec on August 31, 1971, where they spoke to the Vice- President of the supplier company who showed them the objects in question. His evidence about his inspection of them is as follows:
They were all boarded up. All the doors and windows were surrounded with plywood sheets, and Captain Kuyper and I proceeded to verify the dimensions by actually a measuring tape. And then the next question, of course, was: "What do these units weigh?" We were told by Terco [sic] that the dimensions, they could see no way this could be done on public scales because of the location of the public scale in Quebec area, and that really the, the, the, if anybody was interested in the weight, this would be up to the shipper, Jasmin Construction. They then referred us to Jasmin Construction, that if Jasmin Construction wanted to make the necessary arrangements for having the units weighed before shipment, well, this would be up to them, whatever means they could find available.
BY THE COURT:
In other words, the manufacturers claimed they had no knowledge of what they would weigh?
BY THE WITNESS:
No, they said the weights were "approximately".
This visit resulted in the respondent returning to the appellant about the question of weights and Mr. Tomter describes the resulting discussion with the'appellant as follows:
Q. Fine, so the next day did you go back to Jasmin?
A. We went back to Montreal and we got in touch with Jasmin and we told them that we were leery about these units, that they were of course higher than a normal prefabricated house in that they had this, about four (4) feet crawler space in the bottom which con stituted a sort of a basement, and we told Jasmin that we would like for them to make the arrangement of having them weighed, to have the weight verified. It was Mr. Proulx we were talking to, I was speaking to about this, and Mr. Proulx took this very lightly, I would say; he smiled and said: "Don't worry about it. These weights are probably much less than these weights we have indicated to you. These are maximum weights." And that we had nothing to worry about.'
' Mr. Proulx was heard as a witness and he denied having ever given any such assurance. Both he and Mr. Jasmin testified that they had indicated that the weights of 30,000 and 20,000 were approximate weights.
In the meantime, on August 27, 1971, the respondent had sent to the appellant a telex reading, in part, as follows:
[TRANSLATION] IT IS AGREED BETWEEN MESSRS JASMIN CON STRUCTION INC., SHIPPERS, AND FEDERAL COMMERCE AND NAVIGATION CO. LTD., AGENT FOR MESSRS RESOLUTE SHIP PING LTD., SHIPOWNERS, THAT THE AFOREMENTIONED PAR TIES ABSOLUTELY UNDERTAKE:
1. THE SHIPPER TO MAKE AVAILABLE, AND THE SHIPOWNER TO CARRY, THE FOLLOWING CARGO:
14 HOUSE TRAILERS OF THE SIZES DESCRIBED BELOW:
12 UNITS 52 FEET LONG
12 FEET WIDE 14 FEET HIGH
2 UNITS 52 FEET LONG
8 FEET WIDE 14 FEET HIGH
(HEIGHTS EXCLUDING WHEELS, WHICH MAY BE REMOVED WITHOUT DIFFICULTY AT THE OPTION OF THE SHIPOWNER) TWO UNITS WEIGH 30,000 LBS AND THE TWELVE OTHERS ABOUT 20,000 LBS EACH.
WITH THE UNITS ARE INCLUDED ABOUT THIRTY TONS OF BUILDING MATERIALS WHICH THE, SHIPOWNER MAY USE FOR TRIMMING, BUT THE LENGTHS OF WOOD SHALL UNDER NO CIRCUMSTANCES BE CUT.
2. THE SHIPOWNER SHALL TRANSPORT ALL UNITS ON THE DECK OF THE M.V. "TRULELAND", BRITISH REGISTRY AND CLASSIFIED "LLOYDS ICE CLASS 1", OR OTHER SUBSTITUTE VESSEL. THE SHIPOWNER SHALL MAKE AVAILABLE A VESSEL WHICH WILL BE APPROVED BY THE "C.T.C."
3. APPROXIMATE DATES OF LOADING: SEPTEMBER 15, 1971.
4. FREIGHT PAYABLE BY THE SHIPPER TO THE SHIPOWNER: C.C. $14,000 (FOURTEEN THOUSAND DOLLARS) PER UNIT ON A MINIMUM OF FOURTEEN UNITS. ON COMPLETION OF LOAD ING AT QUEBEC CITY THE TOTAL FREIGHT IS EARNED, WHETHER OR NOT THE VESSEL AND/OR GOODS ARE LOST DURING THE VOYAGE.
5. THE SHIPPER SHALL DELIVER THE UNITS TO THE WHARF AT QUEBEC CITY; THE SHIPOWNER SHALL LOAD AND DELIVER IN 1971 SEVEN UNITS TO THE SITE AT BROUGHTON ISLAND AND SEVEN UNITS TO THE SITE AT CLYDE RIVER, BAFFIN ISLAND, AT WHICH LOCATIONS THE SHIPPER WILL USE A BULLDOZER WITH THE NECESSARY ATTACHMENTS TO REMOVE THE UNITS FROM THE BARGES.
6. NO INSURANCE ON THE VESSEL, EVEN IF INCURRED ON A VOYAGE TO THE AFOREMENTIONED LOCATIONS, SHALL BE PAYABLE BY THE SHIPPER.
7. THE SHIPPER SHALL BE RESPONSIBLE FOR ALL INSURANCE PREMIUMS REQUIRED ON THE CARGO FROM THE WHARF AT QUEBEC CITY TO THE SITES AT BROUGHTON ISLAND AND CLYDE RIVER.
8. ON MONDAY, AUGUST 30, 1971 THE SHIPPER SHALL PRO VIDE THE SHIPOWNER WITH A LETTER OF CREDIT IN THE AMOUNT OF ONE HUNDRED AND NINETY-SIX THOUSAND DOL-
LARS; THE TEXT OF THIS LETTER SHALL BE SUBMITTED TO THE SHIPPER BY SHIPOWNER ON MONDAY, AUGUST 30, 1971.
On September 7, 1971, the respondent's parent company wrote to the appellant as follows:
In accordance with your telex of September 2, 1971 you agreed to clause 1, 2, 3, 4, 5, 6, 7 and 9 of our telex to you of August 27, 1971.
We now confirm our subsequent conversations to the effect that your proposed changes to clause 8 set out in your telex of September 2, 1971 are revoked and that you agree instead to furnish us a letter of credit in the terms and conditions, as per the attached sample in the amount of $196,000. This letter of credit will be given to us within 7 days of the date of this letter.
In addition the proposed additional clause 10 will be replaced by the following.
[TRANSLATION] Running gear will have to be returned to Montreal in 1971 if possible; if not, to some other port or ports at our convenience.
Could you kindly sign this letter and return the original to us to signify your agreement to the foregoing.
That letter was accepted by the appellant.
When the officials of the respondent respon sible for loading and unloading the objects in question saw them on the dock on Friday, Sep- tember 17, 1971, there was some alarm. Micha- el O'Connor, for the respondent, testifies:
Q. Now, Mr. O'Connor, could you tell the Court basically what, how you planned to do this job and how you planned and what you planned to do in Quebec, and what happened?
A. Yes. Captain Garvie told me over the telephone what we had to load, and how we proposed to load this cargo, and I asked him the weights of each piece and he gave me two (2) units of thirty thousand (30,000) pounds maximum and twelve (12) units of twenty thousand (20,000) pounds maximum. He indicated to me that these were maximum weights, and from the conversations he had with our Head Office in Mont- real, it was his feeling that the units, that the weights he gave me were maximum, and we discussed the capacity of the gear and the capacity of the crane we intended to purchase or rent in order to help to dis charge these units at their destinations, Broughton Island and Clyde River. If I remember right, Lou Parker and I arrived in Quebec on a Friday. We immediately looked around at the units that were on the dock, and I said to Captain Garvie, I said: "There are no weights stencilled on these units" and he said: "Well, we have got the weights from the Head Office; these must be the weights." Well, I said, "it is very unusual to have the units like this and no weights stencilled on them," and I kept insisting that we got
the proper weights inasmuch as I had a big responsibil ity in that I had to, I had to really worry about how those units got off on Broughton Island or Clyde River.
Nevertheless, the respondent proceeded to build cribbing on the deck of the ship assigned to the contract on the assumption that the units did not weigh more than 20,000 lbs and 30,000 lbs, respectively, and made their plans on the basis of lifting the units from the dock to the deck of the ship with equipment that could not be used with any degree of safety with objects weighing more than 30,000 lbs.
On Sunday, September 19, 1971, the respond ent made its first "lift" of one of the objects and the "Crane lost balance" with the result that the unit fell across the gunwale and became partial ly submerged.
A decision was then taken by the respondent to weigh the other objects (house trailers) that were still on the wharf; and, on Tuesday, Sep- tember 21, 1971, the respondent's parent com pany sent to the appellant a telex reading as follows:
M.S. "TAVASTLAND" AT QUEBEC LOADING PREFAB HOUSING UNITS FOR
BROUGHTON ISLAND AND CLYDE RIVER N.W.T.
REFERENCE MOVEMENT 14 MOBILE HOUSING UNITS FROM QUEBEC TO BROUGHTON ISLAND AND CLYDE RIVER, WE REFER YOU TO OUR TELEX DATED AUGUST 27TH, 1971, PARTICULAR LY CLAUSE NO. 1, IN WHICH THE WEIGHTS OF THE UNITS WERE SPECIFIED AS FOLLOWS:
[TRANSLATION] "TWO UNITS WEIGH 30,000 LBS AND THE TWELVE OTHERS ABOUT 20,000 EACH."
AND YOUR TELEGRAM OF SEPTEMBER 2ND, 1971 IN WHICH YOU ACCEPTED THE OFFER INCLUDING ACCEPTANCE OF CLAUSE NO. 1 SPECIFYING THE WEIGHTS OF THE UNITS.
AS ALREADY NOTIFIED IN OUR TELTEX OF THIS MORNING, (SEPTEMBER 21ST, 1971 AT 11:11), IT HAS COME TO OUR ATTENTION THAT APPARENTLY SOME OF THE SPECIFIED UNITS ARE IN EXCESS OF THE WEIGHTS STIPULATED AND AGREED. SPECIFICALLY, AS A RESULT OF WEIGHING TODAY BY DYNOME- TER, THE FOLLOWING WEIGHTS HAVE BEEN ESTABLISHED:
BLUE NO. 1 27,400 LBS.
BLUE NO. 4 30,800 LBS.
RED NO. 1 28,200 LBS.
FURTHER WEIGHING IS BEING CONDUCTED AND WE HOPE TO BE ABLE TO ESTABLISH THE WEIGHTS OF ALL UNITS WHICH HAVE
NOT YET BEEN LOADED. THIS WILL INCLUDE ALL 7 OF THE BLUE UNITS.
IT APPEARS THAT THE ACTUAL WEIGHTS OF THE UNITS ARE MUCH IN EXCESS OF THE SPECIFIED AND AGREED WEIGHTS, ESPECIALLY INSOFAR AS IT SHOULD BE BORNE IN MIND THAT THE WEIGHTS ORIGINALLY SPECIFIED AND AGREED WERE INCLUSIVE OF RUNNING GEAR AND THE WEIGHTS OUTLINED ABOVE ARE WITH THE RUNNING GEAR REMOVED. AS A PROVI SIONAL ESTIMATE THE RUNNING GEAR IS ESTIMATED TO BE ABOUT 1800 LBS PER UNIT. WE BRING TO YOUR ATTENTION THE FACT THAT THE STABILITY OF ANY VESSEL IS CRITICALLY AFFECTED BY THE WEIGHT OF CARGO ON DECK AND AS PER PROVISIONALLY STIPULATED AND AGREED WEIGHTS IT WAS ANTICIPATED THAT THE 14 UNITS WOULD TOTAL APPROXIMATE LY 150 SHORT TONS. THE ENTIRE STABILITY CALCULATIONS FOR THIS VOYAGE WERE BASED UPON THESE WEIGHTS TO GETHER WITH A REASONABLE MARGIN FOR SECURING MA TERIAL, ETC. AND PERHAPS SOME MINOR FLUCTUATION IN ACTUAL WEIGHTS OF THE UNITS. AT NO TIME COULD IT HAVE BEEN FORESEEN THAT THE WEIGHTS OF THE UNITS MIGHT TOTAL AS MUCH AS 40 OR 50 SHORT TONS MORE THAN AGREED.
WE BRING TO YOUR ATTENTION THE FACT THAT THE ADDITION AL WEIGHT OF 50 TONS WOULD BE EQUIVALENT TO AN INCREASE OF 30 PERCENT OF THE ACTUAL WEIGHT STIPULATED.
IN VIEW OF THE FOREGOING WE PUT YOU ON NOTICE AS FOLLOWS:
1. YOU ARE AT LIBERTY TO CHECK OUR WEIGHING PROCE DURES. IF YOU CAN, WE WOULD WELCOME YOU PRODUCING OFFICIAL WEIGHT CERTIFICATES OUTLINING THE WEIGHTS AS STIPULATED AND AGREED IN TELTEXES REFERRED TO ABOVE.
2. IF YOU ARE ABLE TO EFFECT WEIGHT REDUCTION WITH OUT DELAYING THE LOADING OPERATION YOU MAY DO SO AND IN THIS REGARD WE URGE YOUR URGENT ACTION.
3. WE HOLD YOU ENTIRELY RESPONSIBLE FOR ALL CONSE QUENCES, DAMAGES AND/OR LOSSES THAT MAY OCCUR THROUGH THE EXCESSIVE WEIGHT OF THESE UNITS.
IN THIS REGARD THE VESSEL HAS BEEN EQUIPPED WITH CERTAIN CRANES, ETC. DESIGNED TO LIFT THE UNITS AS ORIGINALLY SPECIFIED. WE HOLD YOU RESPONSIBLE FOR ANY DAMAGE THAT MAY BE CAUSED TO THIS EQUIPMENT, AND WE HOLD OURSELVES HAMLESS [SIC] TO ANY DAMAGE THAT MAY BE CAUSED TO THE CARGO THROUGH THE EXCESS WEIGHTS.
4. WE HOLD YOU RESPONSIBLE FOR PAYMENT OF ADDITION AL FREIGHT IN PROPORTION TO THE EXCESS CARGO WEIGHT OVER THAT ORIGINALLY STIPULATED.
IN ORDER THAT THE ABOVE STATEMENTS CAN BE CLEARLY RECORDED WE INTEND TO APPOINT AN INDEPENDENT SUR VEYOR IMMEDIATELY TO ASSESS THE FACTS AS STIPULATED ABOVE AND WE INVITE YOU TO APPOINT YOUR OWN SURVEY OR TO REPORT EITHER ON A JOINT SURVEY BASIS OR AN INDEPENDENT SURVEY BASIS.
IN VIEW OF THE EXTREME URGENCY OF THIS ENTIRE OPERA TION WE INTEND TO MITIGATE DAMAGES AS BEST AS CAN BE BY PROCEEDING WITH THE LOADING OPERATION AND WITH THE TRANSPORTATION OF THESE UNITS TO DESTINATION.
THERE IS NEITHER THE TIME NOR OPPORTUNITY AT THIS MOMENT TO UNDERTAKE ANYTHING OTHER THAN THE SUR VEYS AND WEIGHING OPERATIONS AS OUTLINED ABOVE.
WE NEED HARDLY TELL YOU THAT AS PROFESSIONAL SHIP- OWNERS AND OPERATORS WITH EXPERIENCE IN HANDLING NUMEROUS PROJECTS OF SIMILAR DIFFICULTY THAT WE CON SIDER THIS APPARENT CARELESS REGARD FOR ACCURATE INFORMATION TO BE OF A MOST SERIOUS NATURE IF FOR NO OTHER REASON THAT IT SUBJECTS OUR PERSONNEL AND EQUIPMENT TO UNNECESSARY HAZARDS.
WE WOULD APPRECIATE YOUR ACKNOWLEDGING RECEIPT OF THIS TELTEX BY TELEGRAM.
There is no evidence of any reply to this telex but it was established that the objects presented by the appellant for carriage under the contract weighed some 30% more than the weights given in the telex of August 27, 1971. Nevertheless, the respondent re-built the cribbing on the deck of the ship to carry the greater weight and successfully made the extra expenditure and incurred whatever risk was involved in carrying out the carriage of such objects in accordance with the terms of the telex of August 27. The reason for carrying such objects in this way even though they so grossly exceeded the weights contemplated by the contract were given by Mr. Bell, Executive Vice-President of the respondent, as follows:
BY THE COURT:
You said that had you known the weight, you would never have undertaken the contract, but in effect when
you did know it, you went ahead with it anyway?
BY THE WITNESS:
Yes. Well, you know, my Lord, when you are faced with something like this and your reputation is on the line, we didn't at this point want to consider anything but getting our units up there. Our customer Jasmin had the government in on this a great deal, and the government put a tremendous amount of pressure on us to perform this job. They wanted those units like they really wanted them in the north, and they were twelve (12) months late as it was, at this time, because others had refused to lift even though they had origi nally stated they would lift.
Q. But once you knew the proper weights of the units, why did you accept to transport them?
A. Because we have a job to perform. We were given the units—
Q. But you knew the risks at that time?
A. We knew them and took them because we had to—
Q. Why?
A. To get the cargo up there, you mean?
Q. Yes.
Q. Well, you meant that you accepted the risks—when the ship left Quebec, you knew exactly the risks it was involving in accepting the cargo?
A. We knew all the time that the vessel, once she left Quebec, had on her fourteen (14) units which were different from the fourteen (14) units that had been described to us initially. We had to have some very expert stevedores who managed somehow to get that cargo off even though they were stretching their own capacity to the full extreme.
Q. You said at first that the first figures you had about the weights of the units, that the ship itself, it was in its limit capacity, so after that you learned that the units were weighing more than that and you accepted to travel those units up to the north?
A. We managed to do it. Isn't that good enough? The ship was straining in all respects, and in fact, in retrospect, I perhaps, it would be true to say that we should have said, "Listen, we are not going to perform this for you." But at the time when we, we acknowledge and we are acknowledged as having more experience than other people, we will do almost anything to perform a contract that is given us to perform. If in good faith our customer had come to us and said we have a very difficult job to do, and we take it on knowing that it is a very difficult job, you have got to go a very, very long way to get a company like ours actually stop doing it.
Q. Well, you didn't think about leaving the ship at the wharf for a few days and negotiate another contract?
A. It shows that you know very little about the Arctic. If I might be allowed to suggest that we had left it more than another day or two, that cargo would never have got there. After all, there is such a thing as heavy freezing up there and you just can't get in after.
Q. Did you know at the time in the harbour that you were going to have some difficulties with the weight on the ship?
A. Oh, quite clearly. We said that quite clearly in our telexes to you.
Q. And you went on?
A. We did, because we are that sort of people. We don't give up if we can see any possible way of doing it. After all, it was public knowledge and we knew that these units were desperately needed. People had told us—
Q. Who told you?
A. I think the government. The government in Ottawa had come to us and said, these are already twelve (12) months behind time.
Q. You were talking a few times about the pressure of the government. How do you know that?
A. Because they came to my office and actually made a plea to me to perform this function if we humanly could.
Q. You never thought about leaving some units on the wharf?
A. I don't know what the hospital unit which is in seven (7) bits and it hasn't got the operating theatre, what it would be like, but we did think of leaving some behind but it was clearly told to us that the whole thing depended on getting it all there. After all, if you don't get the anesthetic room and the operating room it isn't much use.
The loading was completed and the ship sailed midnight of September 24-25.
The principal part of the $36,787.18 claimed by the respondent (all except top wharfage in the sum of $185.58 and $1,000 for insurance) would seem to be based on the costs incurred by the respondent as a result of the weights of the objects carried being in excess of those stipulated in the contract. The amount claimed was the amount by which the respective costs actually incurred by the respondent were claimed to be in excess of those estimated by the respondent as the basis for making its fixed price offer for the transportation operation. We have, in setting out the facts and evidence up to this point, restricted our references to the facts and evidence that related to the amount so claimed and will return later to the other, rela tively minor, amounts, and to the counterclaim.
The learned Trial Judge's Reasons for Judg ment read in part as follows:
I cannot accept defendant's contention that the weight of the units was not material since the price quoted did not depend on the weight but was for a fixed price of $14,000 per unit. Neither can I accept defendant's contention that plaintiff was imprudent in not arranging to have the units
weighed before commencing loading them. The units in question were manufactured according to defendant's own plans and specifications by the Treco Company, a manufac turer acting for defendant. It was defendant who furnished to plaintiff the information as to their approximate weights, allegedly having obtained this information from Treco, and these weights were included in the contract. Plaintiff's rep resentatives did inspect the units in the yard of Treco with a view to seeing their general appearance so as to determine the manner in which hooks or lifting equipment could be attached to them, and to verify the overall dimensions given, but no further information was given them as to the weight. They were told they could not be weighed on public scales and the Treco representatives referred them back to the defendant Jasmin for figures as to their weight. Plaintiff's representatives again asked Mr. Proulx of the Jasmin com pany if the weight figures were correct and he said that there was nothing to worry about as they probably weighed less than the figures given. Certainly the defendant, as designer of the units, and the Treco company as manufac turer of them should be expected to know the weight of the units within a reasonable range of accuracy and plaintiff was entitled to rely on the information given. I cannot find that a difference between 150 tons and 215 tons is a, small or immaterial difference especially when all parties knew that this cargo was to be carried on deck to the arctic near the close of the navigation season there.
I am satisfied that there was error in the contract as to the substance of the thing which was the object of it in view of the weight, and that this weight was a principal consider ation for making it within the meaning of article 992 of the Quebec Civil Code which reads as follows:
992. Error is a cause of nullity only when it occurs in the nature of the contract itself, or in the substance of the thing which is the object of the contract, or in some thing which is a principal consideration for making it.
and that this error was induced by the representations of defendant as to the weight of the units, even though these representations may have been made in good faith. Plaintiff would therefore have been justified in refusing to carry out the contract. This course of action would have caused very heavy damage to defendant which was under pressure from the government to get the units in question delivered. They had been ready for nearly a year but defendant had appar ently been unable to arrange for a ship willing to carry them to the arctic at a price which it was prepared to pay. There was some indication in the evidence that several other shipping companies had been asked to tender for the con tract but either they had not done so or defendant had not accepted their tender. The navigation season was about to close and if plaintiff had decided not to carry the units in question because of the excess weight and to abandon them where they were on the dock at Quebec, it is highly probable that no alternative arrangements could have been made and the delivery would again have been delayed until the follow ing summer.
The fact that plaintiff undertook to carry them despite the great increase in weight and the very hazardous nature of the voyage resulting from this does not, I believe, deprive it of any claim against defendant for additional expenses directly attributable to the increase in weight for which defendant should be held responsible. As soon as the increase in weight was ascertained, the plaintiff advised defendant of this by telex dated September 21, 1971, notify ing defendant that it would be held responsible for the consequences. Later the same day a more detailed telex gave the weights which had already been established for four of the units which had been weighed, referred to the extent to which they exceeded the weight stipulated in the contract and how this would affect the stability of the vessel and gave formal notice that defendant would be held respon sible for all consequences, damages or losses that might occur through the excessive weight, including damages to the crane and equipment of the vessel. It further stated that plaintiff would hold itself harmless for any damage caused to the cargo through the excess weight, and that defendant would be held responsible for payment of additional freight in proportion to the excess of the cargo weight over that originally stipulated. This latter stipulation was never enforced and plaintiff's claim does not include anything for extra freight charges based on the weight of the units as finally determined, and in fact it is doubtful whether plain tiff could have succeeded in a claim on this basis in view of the fixed price contract, without a new agreement with defendant. The telex went on to state that:
In view of the extreme urgency of this entire operation we intend to mitigate damages as best as can be by proceed ing with the loading operation and with the transportation of these units to destination.
Neither of these communications were acknowledged although defendant did have a representative, Leandre Turcot, its Construction Foreman, present during part of the weighing. In a further telex of September 25 advising that the ship had sailed, reference was again made to an eventual claim for compensation for excess weight. Defendant cannot therefore be said to have agreed to plaintiff's conditions for continuing to carry out the contract, nor did it admit that there had been any breach of contract, maintaining through out that the weight was immaterial. It did, however, benefit from the fact that plaintiff completed the contract success fully and since plaintiff was put to considerable additional expense in carrying it out as a result of the excess weight, defendant would benefit by an unjust enrichment and plain tiff suffer a corresponding impoverishment if it were not compensated for these additional expenses resulting from the fault of defendant in giving highly inaccurate informa tion as to the weight of the units.
The learned Trial Judge then proceeded to calculate the additional expenses incurred by the respondent as a result of the excessive weight of the cargo. He assessed those expenses
at $24,722.88, which sum he awarded the respondent.
It should first be observed that if the respond ent's claim is founded on unjust enrichment, as held by the Trial Judge, then the compensation to which the respondent is entitled should not be assessed in the way that was adopted by the Trial Judge. On the basis of unjust enrichment, the only obligation of the appellant would be to pay to the respondent an amount equal to the value of the services rendered by the respond ent; it would not be to compensate the respond ent for the additional expense incurred by it as a result of the excessive weight of the cargo.
A second, and more fundamental, observation indicates clearly that the action is founded on breach of contract; it is not based on unjust enrichment. In our view, it was not open to the Trial Judge, if he were of opinion that the claim for damages could not succeed, to allow it on the basis of unjust enrichment.
When it was realized, at the hearing of the appeal, that it could perhaps be argued that the statement of claim did not allege all the causes of action that could be invoked, it was suggest ed to counsel that he should envisage the possi bility of amending the statement of claim 2 . After a recess, counsel for the respondent applied for leave to amend by adding a new paragraph to the statement of claim alleging, as an alternate basis of the claim, the liability in tort of the appellant. Counsel for the appellant
a Rule 1104 reads as follows:
Rule 1104. (1) At any time during the pendency of an appeal or other proceeding in the Court of Appeal, the Court may, upon the application of any party, or without any such application, make all such amendments as are necessary for the purpose of determining the appeal or other proceeding, or the real question in controversy between the parties as disclosed by the pleadings, evi dence or proceedings.
(2) An amendment may be made under paragraph (1), whether the necessity for the same is or is not occasioned by the defect, error, act, default or neglect of the party applying to amend.
(3) Every amendment shall be made upon such terms as to payment of costs, postponing or adjourning a hear ing or otherwise, as to the Court seem just.
did not oppose that application which was, therefore, granted.
In these circumstances, the question to be answered on this appeal, in relation with this part of the respondent's claim, is whether the respondent is entitled to recover from the appel lant, as contractual or delictual damages, the amount of the loss it suffered as a result of the excessive weight of the cargo.
Inasmuch as the claim is based on breach of contract, we are of the opinion that it cannot succeed for the very simple reason that the loss suffered as a consequence of the weight of the cargo did not result from any breach of the contract by the appellant. In our view, the con tract of affreightment was a contract for the carriage of specific objects previously agreed upon. In delivering those objects on the dock near the respondent's ship, the appellant per formed one of its obligations under the contract and the fact that both parties might have been mistaken as to the weight of those objects did not constitute a breach of the contract on the part of the appellant.
But can the claim of the respondent succeed inasmuch as it is now based on the delictual liability of the appellant company which, by its fault (this fault consisting of the giving of inac curate information on the weight of the cargo) would have caused the respondent to agree to carry the cargo for too low a price?—We do not think so. In our view, the evidence shows that, before the formation of the contract, the respondent was fully aware that the weights that had been mentioned earlier were only approxi mate weights. In those circumstances, it is our opinion that the fact that the respondent never theless agreed to carry the cargo for what it now considers to be an insufficient price (without any undertaking on the part of the appellant to pay any additional charges), was not due to any fault on the part of the appellant but, rather, to the respondent's determination to enter into that contract in spite of the risk that the information it had received as to the weight of the cargo might prove to be inaccurate.
We are therefore of the opinion that the respondent is not entitled to the damages claimed as a result of the excessive weight of the cargo.
In addition to the damages resulting from the weight of the cargo, the learned Trial Judge allowed the respondent sums of $110.61 and $1,000.00. His decision, in respect of those amounts, should not be disturbed. The sum of $110.61 represents the amount of a toll that the respondent had to pay to the National Harbours Board under a by-law adopted under the Na tional Harbours Board Act. Under the by-law, that toll, which is imposed on the cargo and is payable by the carrier, can be recovered by the carrier from the shipper. As to the sum of $1,000.00, it was paid by the respondent in order to insure its freight. Under the contract, the appellant was to supply the respondent, before September 14, 1971, with a letter from a bank guaranteeing the payment of the freight. This, the appellant failed to do. As a conse quence, the respondent thought it necessary to insure its freight and, for that purpose, paid a premium of $1,000.00. In our view, that dis bursement was a reasonable one for the respondent to make in the circumstances and can be considered as having been made as a result of the appellant's failure to perform one of its obligations under the contract.
For these reasons we are of the opinion that the Judgment of the Trial Division which allowed the respondent's claim should be varied by reducing its amount from $25,833.49 to $1,110.60.
We now turn to that part of the judgment of the Trial Division which, disposing of the appel lant's counterclaim, for alleged damages to the cargo, allowed the appellant $676.90. Against that judgment the appellant appeals and the respondent cross-appeals.
The respondent submits that the appellant's counterclaim should have been dismissed in so far as it relates to damages to goods that were not the object of the contract of carriage.
It is common ground that at least part of the damages awarded to the appellant on its coun-
terclaim represents compensation for damages to some plumbing supplies which, unknown to both parties, had been stored in the crawlspace of the hospital unit that fell overboard at the time of the loading at Quebec. The contract did not contain any reference to this box of plumb ing supplies and it is for that reason that the respondent submits that it had no obligation whatsoever respecting their carriage. We cannot agree with that submission. The contract was for the carriage of specific mobile units which, as the respondent knew, were to be assembled into two hospitals. Even if the contract did not mention the presence of the box of plumbing supplies in one of the units, it was reasonably foreseeable in the circumstances, that those units would contain the fittings that were neces sary for the assembly and the completion of the hospitals. For this reason, we are of opinion that the respondent's cross-appeal against that part of the judgment must fail.
It is the appellant's submission, however, that its counterclaim in the amount of $2,707.61 should have been allowed in full.
If the Trial Judge allowed only one-fourth of the appellant's counterclaim, it is because he considered
(a) that it related to damages caused by the fall overboard of one of the units at the time of loading, and
(b) that the fall of the unit had been caused, in the proportion of one-fourth, by the negli gence of the crane operator, and in the pro portion of three-fourths by the negligence of the appellant in giving inaccurate information as to the weight of the cargo.
We cannot agree with the finding of the learned Trial Judge that the accident which took place at the time of the loading was attributable to the appellant's fault. At the time of the loading of the cargo, the respondent knew that the infor mation it had received as to the weight of the units might not be accurate. In these circum stances, the respondent had the duty either to ascertain the weight of the units before loading them or to use a crane powerful enough to lift weights much heavier than those mentioned by the appellant. The fall of the unit at the time of loading was, in our view, caused exclusively by
the respondent's negligence to perform that duty.
It is therefore our opinion that the learned Trial Judge should have allowed the sum of $2,707.61 to the appellant on its counterclaim.
For these reasons the appeal of the appellant against the judgment in the main action will be allowed and the amount awarded the respondent by that judgment will be reduced from $25,833.49 to $1,110.61 with interest; the appeal of the appellant against the judgment on the cross-demand will be allowed and the amount awarded the appellant by that judgment will be increased from $676.90 to $2,707.61 with interest; the cross-appeal of the respondent will be dismissed.
The appellant will be entitled to its costs of defending the main action in the Trial Division and to its costs of the appeal from the judgment in the main action; neither the appellant nor the respondent will be entitled to any costs, either in the Trial Division or in this Court, with respect to the cross-demand and to the appeal and cross-appeal from the judgment on the cross-demand.
* * *
HYDE D.J.—I concur.
 You are being directed to the most recent version of the statute which may not be the version considered at the time of the judgment.