Judgments

Decision Information

Decision Content

T-1680-77
Alftar Construction Inc. (Plaintiff)
v.
The Queen (Defendant)
Trial Division, Dubé J.—Montreal, December 11, 1979; Ottawa, March 18, 1980.
Crown — Contracts — Plaintiff claiming an amount for additional costs and loss of time from the performance by it of a public works contract — Ambiguity of contract with respect to work on ceiling interpreted in plaintiffs favour but unfair and unproved accounts disallowed — Plaintiffs claim for additional costs of conduits for the telephone system that were not shown on the plans was dismissed as it was industry practice not to show such detail except in specifications — Claim for time lost and loss of earnings dismissed because they were neither established nor the financial responsibility of the owners — Interest allowed on the $5,000 awarded the plaintiff pursuant to formula provided in the contract — Federal Court Act, R.S.C. 1970 (2nd Supp.), c. 10, s. 35.
ACTION. COUNSEL:
R. Talbot for plaintiff.
J. Ouellet, Q.C. for defendant.
SOLICITORS:
Mercure & Côté, Laval, for plaintiff.
Deputy Attorney General of Canada for defendant.
The following is the English version of the reasons for judgment rendered by
Dust J.: Plaintiff ("Alftar") is claiming from the Department of Public Works the total amount of $43,237.09 in additional costs and loss of time resulting from the performance by it of a public works contract, for work to be done on a Canada Manpower Centre inside a federal building in Chicoutimi, Quebec.
The contract, with plans and specifications, was concluded on August 30, 1976, in the amount of $100,690.
The claims based on additional work relate to two different heads: unforeseen demolition of the existing ceiling ($34,306.93) and installation of unforeseen telephone conduits ($4,851.33).
1. Demolition of the existing ceiling
Alftar alleged that neither the plans nor the specifications contained any specific and special provision that the work to be done included demo lition of the existing ceiling. Defendant admitted that the demolition was not indicated in the plans and specifications, but maintained that the necessi ty for such a demolition was obvious since the contract provided for a new ceiling 8'S" from the floor, while the elevation of the old ceiling was between 8'6" and 8'7 1 / 4 ".
Plaintiff maintained that it expected to suspend the new ceiling from the old; according to the expert witness for plaintiff, this was a plausible and practical solution, while the architect for the Department, who drew up the plans and specifica tions himself, considered that such a solution could not be used in this location.
The ceiling in question was 10,000 sq. ft. of plaster, weighing some sixty tons. The ceiling included various trapdoors, and there was a space of 15" between the ceiling and the beams, allowing for the installation of air intakes and electrical conduits. According to the president of Alftar and the engineer called as an expert witness, this space was more than sufficient to allow the new ceiling of acoustical tiles to be attached. It was admitted that such a working method is currently used when space permits.
The list of the work to be done is found in clause 1.2.301 of the specifications and contains twenty- one different items. It includes demolition of the existing partitions, but not demolition of the ceil ing in question. In clause 2.1.301, titled [TRANS- LATION] "Extent of the Work" there is a reference to [TRANSLATION] "complete demolition of the interior partitions" and also to the demolition of [TRANSLATION] "all wires, intakes, plumbing and electrical and ventilation equipment not required in the new plan". There is no specific reference to the ceiling.
The specifications in question were general specifications used as a basis for similar renova tions inside various federal buildings. According to the engineer called by the Department, for there to have been a precise provision requiring demolition of the ceiling with reference to the Chicoutimi building, a complete survey of the building would have been necessary. In his view, the size of the contract did not justify such an undertaking.
In my opinion, a specific provision would have avoided any ambiguity and alerted the contractor. In some buildings the existing ceilings must be retained while in others they have to be demol ished: persons preparing specifications cannot assume that the general contractor will necessarily draw the conclusions appropriate to his contract without further clarification. Moreover, under the Civil Code and at common law, in the event of an ambiguity the contract is generally interpreted against the person making the stipulation and in favour of the one undertaking the obligation.
In all justice and equity, therefore, Alftar must be compensated for this unforeseen work, which was indeed performed under protest. However, I find the claim of $34,306.93 to be at the very least exorbitant. The list of costs included in plaintiff's statement of claim contains items which are mani festly unacceptable, such as [TRANSLATION] "air travel, $2,069.70", "restaurant and hotel expenses, $1,478.05". The other amounts claimed for [TRANSLATION] "labour and fringe benefits", "repairs to plaster", and so on, were not proved to have been expenses incurred for demolition of the ceiling in question.
I find to be much more realistic the very impar tial expert opinion of the firm J. Euclide Perron Ltée of Chicoutimi, as presented by the engineer Georges H. Perron of that city. This local engineer benefits from more than twenty-five years of experience in similar work. At the time in ques tion, he would have accepted the demolition con tract for the ceiling at 25¢ a square foot, that is exactly $2,891 for an area of 11,564 feet.
However, the Court must take into consider ation that Perron would have been bidding in ideal circumstances. Plaintiff, on the other hand, was taken unawares and had to reorganize its resources a considerable distance from its base of operations
in Montreal. Allowance must also be made for the fact that, under the agreement, the entire premises was not released when the contract began. Alftar had to work with great care. In the circumstances, I think it would be reasonable to allow plaintiff a more generous sum for demolition of the ceiling, namely the arbitrary amount of $5,000.
Judgment will therefore be given for plaintiff in the amount of $5,000.
2. Additional costs for unforeseen telephone conduits
The problem relating to this claim concerns the interpretation of the first paragraph of clause 16.2.22 of the specifications, which reads as follows:
[TRANSLATION] 16.2.22 System of non-loaded conduits for telephones
This section includes the supplying and installation of a system of non-loaded conduits, pull boxes, junction boxes, output terminals and everything required for the installation of a telephone system, as indicated in the plans.
Under this heading, the subcontractor Grimard Electrique Inc. submitted to Alftar a bill for $2,875 for the addition of a two-inch telephone conduit. Alftar maintained that no provision was made for such a conduit in the clause cited above or in the plans. The electrical engineer Alban Normand, whose firm participated in preparing the plans and specifications for the Department, explained to the Court why it is not necessary to draw the conduits on the plan. They only need to be indicated in the specifications.
The first paragraph of the clause of the specifi cations cited above does stipulate that the contrac tor shall provide and instal a network of non-load ed conduits, and so on, and everything necessary for the installation of a telephone system. Alftar alleged that the phrase [TRANSLATION] "as indicated in the plans" does not apply only to the [TRANSLATION] "telephone system" but to the entire paragraph, and that therefore the conduits should have been indicated on the plans.
The telephone system indicated on the plans showed an equipment room and thirty-nine local ized telephone terminals on the floor.
The expert witness for the Department stated that it was not necessary to show conduits on the electricity plans, as the latter were subject to very specific requirements by telephone companies, and any qualified contractor would be familiar with these requirements. The specifications called for a complete telephone system with conduits, boxes and so on. The plans indicated the extent of the system and the location of terminals, without necessarily showing all components of the system.
The expert witness considered that it was not necessary to indicate conduits on the plans, just as all the screws, nuts, bolts and metal parts are not indicated.
This expert opinion by the engineer Alban Nor- mand seemed to be clear, precise and accurate. The plans and specifications cannot spell out everything to the smallest detail. After all, indus try practice and the competence of the contractor are also involved.
In the case at bar, it would appear that the electrical subcontractor made an error in its bid. It misinterpreted the plans and specifications and accordingly submitted an additional claim to Alftar, which incorporated this into its claim against the Department.
This claim cannot be allowed.
3. Claim for time lost and loss of earnings
An agreement was concluded on July 12, 1976 regarding release of the premises, as reproduced in this letter.
[TRANSLATION] Further to our visit to the office with Mr. R. Girard on the aforementioned project, it is agreed that the premises will be released entirely in the first week of August 1976, except for documentation and the conference room, which will not be released until September 1: the whole condi tional on awarding of the contract on July 16, 1976; at no charge to the Department, and only on the aforesaid terms.
Alftar maintained that this date was not observed. Jean Houle, who was in charge of the project for the Department, went to Chicoutimi on August 10 to meet with the site foreman for Alftar, Marcel Legros, with respect to release of the premises. He returned on August 16, and at that time only the two rooms mentioned above had not been released. There was no direct evidence as to the exact date of release of the principal area between August 10 and 16, or as to the date of the
eventual release of the two rooms. Plaintiff did not call its foreman Legros to establish these dates.
In addition, clause 2.1.303 of the specifications
provides for any financial claim with respect to delay. The clause reads:
[TRANSLATION] 2.1.303 Delay
The demolition contractor may in no way hold the owner financially liable for delays or impediments resulting from whatever cause during the performance of any part or the whole of the work.
However, if the delay was attributable to an act or omission of any kind on the part of the owner, the latter shall allow the contractor sufficient time for completion of the work to offset the delay, but shall in no way be financially liable for delays which may be caused by his own fault. Any delay in this sense shall be determined by the engineer, who shall be responsible for supervising the work.
This claim is accordingly dismissed.
Plaintiff is further claiming interest from the date of the work. According to the provisions of section 35 of the Federal Court Act, R.S.C. 1970 (2nd Supp.), c. 10, the Court only awards interest on an action against the Crown if there is a contract or statute providing for interest in such a case. Alftar submitted its claim for interest in accordance with clause 6 of the heading regarding methods of payment contained in the contractual document. The clause reads as follows:
[TRANSLATION] 6. Delay in payment
A delay by Her Majesty in making a payment when it becomes due and payable under the methods of payment shall be deemed not to be a breach of contract by Her Majesty, but such a delay, if the payment in question is due under paragraph (4) of clause 4 of the methods of payment, and if the delay is in excess of fifteen days, shall entitle the contractor to interest on the amount in arrears, and when Her Majesty pays the amount in arrears she shall pay the contractor interest on the said amount, calculated for the period of the said delay at the rate of 1 1 / 2 % plus the rate of bids accepted for three-month Treasury bills of the government of Canada, in accordance with the announcement made each week by the Bank of Canada on behalf of the Minister of Finance, the said average rate to be that which is announced immediately before the date when payment was first due to the contractor.
Alftar must therefore be awarded interest on the amount of $5,000 calculated in accordance with the foregoing formula.
 You are being directed to the most recent version of the statute which may not be the version considered at the time of the judgment.